Home

 

Department of RevenueBusiness Reengineering/Integrated Tax System (BRITS) (October 2005, Report No. 05-15)

 

 

SUMMARY

The Office of the Auditor General has conducted a performance audit of the Department of Revenue’s Business Reengineering/Integrated Tax System (BRITS) project pursuant to a November 20, 2002, resolution of the Joint Legislative Audit Committee. This audit was conducted as part of the sunset review process prescribed in Arizona Revised Statutes (A.R.S.) §41-2951 et seq and is one of a series of four reports on the Department. The other reports focus on the Audit Division, the Collections Division, and an analysis of the 12 statutory sunset factors.

Background

The Department of Revenue (Department) is responsible for licensing, processing, and collecting over $9.8 billion in taxes for the State of Arizona. The Department is heavily dependent on information technology to perform its functions, but its technology was largely outdated and consisted of many different stand-alone systems. For example, the Department’s system for transaction privilege taxes (better known as sales taxes) was built in 1982 and had reached its technical limits. In addition, numerous stand-alone databases were developed in isolation, resulting in the need to input taxpayer information separately and making it difficult for department staff to quickly view all aspects of a taxpayer’s business with the Department.

In August 2002, the State entered into a contract with Accenture, a global management consulting firm, to reengineer its core business processes, organizational structure, and implement an integrated tax system—BRITS. With BRITS, taxpayer data will be entered in one place, and all taxpayer information will be available through this one integrated system. The project is being implemented in three phases. The first phase involved designing and implementing the main database where all tax processing activities will occur; developing other components to improve the Department’s processes, such as tools to help find taxpayers who have not filed their taxes; and converting transaction privilege and withholding tax data from the Department’s old system to BRITS. This phase has been implemented since October 2004. The second phase primarily includes converting corporate income tax data and is currently in progress. However, according to department management, the expected completion date has been revised from July 2005 to July 2006 to ensure that sufficient time is taken to fully define system requirements, complete user testing, and minimize operational impacts during peak processing times. The final phase primarily involves converting individual income tax data. According to the Department, the scope of this phase has not been fully defined at this time; therefore, a target completion date has not been set. As a part of the BRITS project, the Department received approximately 1,100 desktop and 60 laptop computers and, to facilitate field collections, 50 handheld computers. The contract also includes “additional backfill support,” which appears to be for hiring temporary employees to help maintain the Department’s productivity during BRITS’ implementation and for ordering any needed additional technical support from Accenture staff during implementation. The State’s central procurement office, Enterprise Procurement Services (EPS), has overall authority for the contract, but has delegated contract administration responsibility to the Department.

The contract uses a benefits-sharing funding approach. Under this approach, Accenture is financing the contract’s up-front costs and will be paid, with interest, out of increased enforcement revenue the system is expected to generate. Enforcement revenue is money the Department receives as a result of its enforcement functions, such as audit, accounts receivable, and collections. BRITS is supposed to improve these activities, thereby generating three specific types of enforcement revenue. As provided for by the contract, the Department uses 85 percent of the additional enforcement revenue to pay Accenture’s invoices, and retains the other 15 percent. This allocation continues until the total cost of BRITS, $122.65 million plus an estimated $9-$13 million in interest, is paid. However, if BRITS has not generated enough additional enforcement revenue to pay the contract costs by the end of the contract’s 10-year term, the Department will no longer be liable for the unpaid costs and will keep 100 percent of the additional enforcement revenue generated by the system after that time.

Department needs to better manage BRITS project
(see pages 9 through 18)

The Department could do more to ensure that it effectively manages BRITS implementation and that BRITS will meet its needs. According to the Department, by January 2004, demographic information for the transaction privilege (commonly known as sales tax) and withholding tax types had been converted to BRITS. Information that was converted included taxpayers’ names and registration numbers, and some accompanying financial information for transaction privilege tax accounts, such as the amount taxpayers owed to the State. However, in some cases the data for transaction privilege tax accounts did not convert correctly. Further, due to BRITS’ implementation problems, the Department had to manually review and correct its transaction privilege tax bills before sending them to the taxpayers, in turn causing a backlog of bills to be mailed. For example, as of June 30, 2004, approximately 6 months after beginning to process transaction privilege tax returns in BRITS, bills had not been sent for over 17,000 taxpayer liabilities totaling nearly $45 million.

BRITS’ implementation issues may have been minimized if the Department had hired an outside advisor as outlined in the BRITS contract. The BRITS contract contains a clause indicating the Department intended to hire an oversight advisor who was not affiliated with the project to report on BRITS’ progress, risks, and budget and make advisory recommendations to the director. Department officials indicated they were not certain why an outside advisor was not hired, but cost may have been a factor. However, hiring an outside advisor may have prevented or at least helped identify and mitigate the BRITS implementation problems. For example, in 2003, Hawaii’s Department of Taxation hired an outside advisor for approximately $200,000 a year to provide quality assurance consultant services for its integrated tax system project. A Hawaii Department of Taxation official who auditors spoke with indicated that using an outside advisor was helpful and that a benefit of such an advisor is that they can alert the agency to things that should or should not be occurring on the project. A BRITS project outside advisor would have been beneficial to the Department. Interviews with the Department indicated that it did not involve a sufficient level of the most knowledgeable department staff, such as IT staff familiar with the previous systems, and the BRITS project has been managed by four different department project managers since the project began. Even though the Department is taking steps to more effectively manage the project, it should still consider hiring an outside advisor to help oversee BRITS’ remaining phases. To do so, the Department would have to examine possible funding methods such as allocating monies from its current budget or seeking a separate appropriation from the Legislature.

Whether or not an outside advisor is hired, the Department needs to continue improving its project management. The Department has taken some steps to conform with best practices for IT project management. For example, for BRITS’ second phase, the Department is involving a greater number of knowledgeable staff and working with Accenture to define in more detail what functions the BRITS system must be able to do. Auditors found, however, that the Department can make additional improvements in a number of areas, ranging from better planning and training to more thorough testing of whether functions actually work. For example, one best practice is to have an overall project plan to help guide the project management. Although Accenture created an overall project plan to guide its efforts, the Department has not created or followed any overall plan to guide its own management of the BRITS implementation.

BRITS not generating additional revenue as expected
(see pages 19 through 24)

BRITS has not generated increased revenue as expected, resulting in negative financial implications for the State. BRITS appears to be generating two of the three types of enforcement revenue that are measured—discovery revenue and license compliance baseline revenue. However, BRITS has not been able to consistently produce the other type of enforcement revenue, efficiency revenue, primarily because of BRITS’ inability to generate accurate bills for taxpayers with unpaid tax liabilities. Based on department information, efficiency revenue has been as much as $27.3 million less than the Department expected to collect even without BRITS, and was approximately $9.3 million less than expected as of March 2005.1

BRITS’ inability to increase enforcement revenue carries negative financial implications for the State. Specifically, because contract payments to Accenture are supposed to be made from increased enforcement revenue, BRITS’ failure to generate efficiency revenue is hindering the State’s ability to make payments. Since Accenture charges interest on unpaid contract costs, this translates to additional interest costs for the State.

The Department and Accenture are taking steps to improve enforcement revenue. For example, the Department has developed a special team of department and Accenture staff that is charged with increasing enforcement revenue by improving existing BRITS discovery programs and creating and implementing new ones. The Department needs to continue these efforts. The Department should also continue to include information about low efficiency revenue in its monthly project status report to the Government Information Technology Agency, which it only began doing in June 2005 in response to auditor recommendations.

Department should better ensure
contract changes are appropriate
(see pages 25 through 30)

In an effort to administer the contract under its indefinite-quantity terms, the Department has made several changes to the contract that may impact its overall scope. In all, the Department has added nearly $7 million of additional services to the contract, including $6.4 million for Accenture to provide offsite data center services. Initially, to keep the total contract price at $122.65 million, the Department decreased the amount of monies available for other tasks. In particular, the Department primarily reduced the amount of monies available for a broadly defined task known as “additional backfill support,” which appears to be for the hiring of temporary employees to help maintain the Department’s productivity during BRITS’ implementation and for ordering additional technical support from Accenture. Although the Department is trying to control the changes’ impact, its method of doing so may increase the contract’s price or require the Department to forego products or services.

Considering the contract changes’ potential impact, it is important that the Department consult department and state contracting officials. Consulting these procurement experts is especially important for the BRITS contract because EPS, not the Department, has overall authority for the contract. However, for the changes the Department has already made, communication was lacking. For example, one of the Department’s project managers signed a memorandum from Accenture indicating she agreed that 5 of 534 original system requirements are not within the contract’s original, overall scope, but did not discuss the agreement with the Department’s procurement office or EPS.

It is also important for the Department to thoroughly document contract changes. This will help ensure that changes that affect the contract’s overall scope are identified and incorporated into the contract. However, documentation for many contract changes either did not exist or did not fully explain how the change affected the scope of the tasks involved.

To its credit, the Department has begun taking steps to improve its communication and documentation of contract changes, and should continue its efforts. For example, on May 17, 2005, the Department sent a memorandum to EPS documenting the contract changes that had already been made and requesting that EPS increase the overall contract price by approximately $6.4 million, to a new total of approximately $129 million, to include the data center costs.2


1 As of September 8, 2005, the Department was in the process of finalizing efficiency revenue calculations for April through June 2005. However, department officials indicate that, based on preliminary calculations, they expect to realize enough efficiency revenue from those months to eliminate the cumulative negative efficiency amount.

2 If EPS increases the contract price to include the data center as requested by the Department, then the Department would no longer have to pay for the data center by reducing the amount of monies available for other contract tasks.


Read full report in Acrobat PDF format
 

 

 
 

 Home | About UsPublications | Careers | Links | Contact Us | Privacy Statement | Webmaster

Copyright 2011 State of Arizona Office of the Auditor General, All Rights Reserved.